Another Billy Trail closure – more improvement

See below for an update from the Havant Transport and Implementation Team. We don’t yet have dates for the closure but will post them here when we do.

It’s good to see more improvement. It’s early days, but the new section seems much better than the southern section, so we’re hoping it will set the standard for future improvements.

Continue reading “Another Billy Trail closure – more improvement”


Billy Trail re-opens following upgrade

The section at the north of the island is now open again, although all users are being asked to treat the new surface with respect while it is bedding in.

There’s also some more work to do that will not require the path to be closed, so please watch out for people working.

Peter Drury’s blog has some photos of the new section and some taken while it was under construction.

We are all hoping that this will prove to be an excellent development that will show the way for future Billy Trail improvements. We’ll be keeping an eye on it as time goes on.

Thanks – once again – are due to Peter Drury who has done so much to bring this about through his Hayling Billy 50 work. I’m sure he’d be the first to point out that it’s been a team effort involving Havant, Hampshire, National Lottery and a bunch of others.

Work about to start at the North end of the Hayling Billy Trail?

The latest progress report on the bridge works (Works Progress 7: 16th April 2014 on this page) says…

We’ll then move off the road and work on the ‘Hayling Billly 50’ Trail rebuilding, completing everything by mid June.

That’s a reference to Lottery-funded project initiated by Peter Drury as part of the Hayling Billy 50 years commemoration.

It looks like something is definitely going to happen. We understand that the project will:

  • Use the same surface as recently laid at the south end of the Billy Trail
  • Resurface a limited section of the trail (and not, as hoped, as far as the Esso Garage)

We are concerned over the quality of recent cycle path development by both Havant and Hampshire so – at Peter’s request – I have documented our concerns with an offer to help. Peter has passed them to the project board.